Q: K can finish the work in 18 days and L can do the same work in 15 days. L worked for 10 days and left the job. In how many days, K alone can finish the remaining work ?

  • 1
    5.5 days
  • 2
    6 days
  • 3
    4.2 days
  • 4
    5 days
  • Show Answer
  • Workspace

Answer : 2. "6 days"
Explanation :

Answer: B) 6 days Explanation: L's 10 days work = 115×10=23   Remaining work = 1-23=13   Now,  work is done by K in one day = 1/18   1/3 work is done by K in  18×13 = 6 days