Q: A constructor estimates that 4 people can paint Mr. Karthik's house in 6 days. If he uses 5 people instead of 4, how long will they take to complete the job ?

  • 1
    3 days
  • 2
    26/3 days
  • 3
    13/4 days
  • 4
    24/5 days
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "24/5 days"
Explanation :

Answer: D) 24/5 days Explanation: we know that m1 x d1 = m2 x d2=> 4 x 6 = 5 x dwhere d = no. of days taken by 5 men to paintd = 24/5 days.